One to two weeks after we’ve signed our agreement and financing is arranged, we’ll be starting actual construction of your new home!
The exact schedule of construction may vary depending upon weather, material deliveries, subcontractor availability and size and difficulty of your custom home. However, the schedule we strive to follow during construction is outlined below. This schedule allows us to build your home expeditiously while maintaining excellent quality control!
| Week |
Task |
- Survey for Home, Dig Basement, Pour Concrete Footers
- Basement Walls Poured, Gravel Basement Floor, Install Drain Systems Ground Plumbing Rough
- Basement, Backfill Basement, Floor Poured
- Frame Walls
- Set Trusses or Rafters, Sheath Roof
- Roof, Hang Exterior Doors, Fascia Installed, Measure for Cabinets, Windows Installed, Garage Concrete Floor Poured
- 2nd Plumbing Rough, A/C Duct Rough, Electrical Rough, Prewire Phone, Intercom & Vacuum System, Sewer/Water Services Connnected, Brick Delivered
- Finish Roof, Wall Insulation Installed, Hang Drywall, Brick Continuing
- Drywall and Brick Finishing, Garage Door Installed
- Ceiling Insulation Installed, Interior Painting, Sidewalks, Drives Constructed
- Trim and Interior Doors Installed, Shelving Installed, Plumbing & Heating Trim Installed
- Electrical Fixtures Installed, Intercom Trim Installed, Final Grade Yard, Final Painting
- Wallpaper Installed, Landscape Planted, Sod Installed, Power Turned On
- Heating & A/C, Electrical & Plumbing Final Check, Mirrors Installed, Touch Up Work
- Carpet Installed, Hardware Installed, Final Cleaning
- Home complete and ready for occupancy
|
|